"Maximum Capacity" 200 Ton Cherry Picker has the lifting tripod rig
ready to unload!
Here is a picture of the reactor
head being lifted off the transporter!
The Trail King S-300 transporter carrying the replacement
Reactor Head is seen
lining up for unloading. The delivery process will take a few hours to perform.
The operational execution of the Delivery phase involves
several key evolutions:
Removal of the load tarp cover from the reactor head;
Attachment of lifting tripod to reactor head lifting slings;
Removal of many cables that held the reactor head secure; and:
Transferring the Midland reactor head from the transporter to the flatbed truck.